MINING PARTNER

PT. BARA ENERGY

Exactly June 19, 2023 SMM COAL ( PT. SUN MENARA MANDIRI ) entered into a cooperation agreement with PT. BARA ENERGY for the production and marketing of coal on the land of PT. GUNUNGBAYAN PRATAMACOAL with MOU Number: 1906/KSO-BAYAN/BLOK-SP/BE -SMM/VI/2023

Coal Mining Summary

Nomor : 1906/KSO-BAYAN/BLOK-SP/BE-SMM/VI/2023


1. Name of IUP OP : PT.GUNUNG BAYAN PRATAMA
2. Number of IUP OP : 05A.K/40.00/DJB/2006
3. Date of issue of IUP OP : Januari 20, 2006
4. Extensive Area of IUP OP : SP Block 2000 Ha
5. Location of IUP OP : Kabupaten Kutai Kartanegara
6. Code of Territory : 05PB0165
7. Land System : Fee for Owner Land
8. Transportation Facility : DT capacity 25 Ton
9. Main Hauling Road : Ex Gn Bayan Road
10. Pit to main hauling road : 2 KM
11. Condition of hauling road : Upgrade and Maintenance
12. Pit distance to jetty : 33 KM
13. Jetty load : GEMIDA
14. Jetty Fasility : Crusher and Conveyor
15. Barge capacity : 300 Feet
16. Anchorage Vessel : Muara Berau
17. Barge mileage : 24 – 30 Hour
18. Coal quality : Vary, GCV GAR 6000 Kcal/kg up (Thermal Coal)
19. Coal Resource : 5.000.000 MT (Measured)

CV. ANUGRAH MAPAN PERKASA

On June 27, 2023 SMM COAL (PT. SUN MENARA MANDIRI) won the trust of working with the owner of the AMP mine (CV. ANUGRAH MAPAN PERKASA), where the AMP land is land with coal quality with Gar 7000 specifications or in other words Anthracite Coal with MOU NUMBER : 2706/AMP-SMM/PK/COAL/VI/2023

Coal Mining Summary

NOMOR : 2706/AMP-SMM/PK/COAL/VI/2023

1. Name of IUP OP : CV. ANUGRAH MAPAN PERKASA
2. Number of IUP OP : 188.45/727/2014
3. Date of issue of IUP OP : Oktober 16, 2014
4. Extensive Area of IUP OP : 1,748 Ha
5. Number of CNC Certificate : 882/Bb/03/2017
6. Date of Issue of CNC Certificate : Agustus 1, 2017
7. Expiry date of IUP OP : Oktober 16, 2034
8. Location of IUP OP : Sub District of Teweh Tengah, District of Barito
Utara, Central Kalimantan
9. Code of Territory : 62.03.14 3 201916
10. Forestry Analysis : APL = 40 dan HPK = 1.708 Ha
11. Land System : Land acquisition with owner
12. Transportation Facility : DT with capacity of 25 MT
13. Main Hauling Road : PT. NANTOY BARA LESTARI (NBL)
14. Pit to main hauling road : Alternatife hauling road 1 km will be open
15. Condition of hauling road : Good, smooth and well-maintained
16. Pit distance to jetty : 3,4 Km
17. Jetty load : PT. NANTOY BARA LESTARI (NBL)
18. Jetty Fasility : Conveyor and loading to barge
19. Barge capacity : 270 ft.
20. Anchorage Vessel : Tabaneo
21. Barge mileage : 40-48 hours
22. Coal quality : Vary, GCV GAR 7400 Kcal/kg (Antrachite Coal)
23. Coal Resource : 2,3 Million MT
24. Community description : For all matters concerning the
surroundingcommunity, we have conducted various negotiations and understandings, and the surrounding community provides positive support and response, and any problems that may arise in the future are entirely our responsibility, and need to be underlined during the mining activities should always be built on good relationships with the community in terms of involving local workforce in accordance with the capacity and skills possessed.